Flinders University is seeking proposals to supply, implement, configure, migrate and support a scalable backup and recovery platform for virtual machines and file shares, as part of its 2026 Infrastructure Refresh Program. The contract is for five years, with a five-year supported solution.
The current environment, described as background rather than a named incumbent firm, uses two Dell ML3 tape libraries (one at Bedford Park and one at a data centre) managed by Dell NetWorker, and two replicated Dell PowerProtect Data Domain appliances managed by PowerProtect Data Manager. The University wants replicated disk backups plus resilient offline copies. Proposals may use tape, hardened cloud storage, or both, if the technical and operational requirements are met. Tape proposals should allow for at least 200 slots and 10 drives. Hardware, if offered, is to be delivered to the Engineering Building at Bedford Park, South Australia.
Ingestion of additional awaiting data is a separate project and is out of scope, but the platform must be able to expand to about double the current working data. Evaluation is expected in January 2027, with contract commencement in March 2027. Responses stay valid for 120 days from close.
The references are FL1680.E and FLINUN-1179200. Responses lodge on TenderLink Flinders using the Part C response template. Close is Friday 11 December 2026, 2:00pm Adelaide time (ACDT), which is 2:30pm Melbourne time (AEDT). Questions close Friday 4 December 2026, 2:30pm Melbourne time. The contract value is not stated.